SAVANNAH - Chatham County has fired the contractor for a parking lot project at the Kings Ferry boat ramp in the southwest portion of the county, delaying access to the ramp by recreational boaters.

County officials say Florida-based RK General Contracting was supposed to complete the $573,000 project by last month, but only about half of it is done.

Officials say the contractor's bonding agent has 25 days to decide whether to find a replacement or let the county bring in someone else.

Suzanne Cooler, a senior engineer for the county, says the project is expected to take up to 60 days to complete once a new contractor is hired.

General Contracting officials could not be reached for comment.

May. 24, 2011 11:44a.m. EDT Kings Ferry landing work delayed Bryan County News

SAVANNAH - Chatham County has fired the contractor for a parking lot project at the Kings Ferry boat ramp in the southwest portion of the county, delaying access to the ramp by recreational boaters.

County officials say Florida-based RK General Contracting was supposed to complete the $573,000 project by last month, but only about half of it is done.

Officials say the contractor's bonding agent has 25 days to decide whether to find a replacement or let the county bring in someone else.

Suzanne Cooler, a senior engineer for the county, says the project is expected to take up to 60 days to complete once a new contractor is hired.

General Contracting officials could not be reached for comment.

Copyright 2011 MorrisMultimedia . All rights reserved. This material may not be published, broadcast, rewritten or redistributed
 

Comments

  • Bookmark and Share

Commenting not available.
Commenting is not available.

Most Popular


Please wait ...